Soil Embankment Placement

20,000 CY

Asphalt Paving

3,300 FT

Asphalt Material

18,000 Tons

Project Details

Following the construction of a new landfill and truck loading station, Trans Ash was awarded a landfill. haul road construction project to connect the two areas. This road would serve to supply CCR fill material to the newly constructed landfill as well as future expansions of the landfill.

Download Case Study (PDF)

Project Challenges & Solutions

Operational Efficiencies

Trans Ash utilized its vast CCR landfill operation experience along with internal AutoCAD Civil 3D Technicians to provide an alternate that would increase operational efficiencies and improve safety.

Project design

Trans Ash proposed a new alignment that reduced cost by straightening the haul road to eliminate the unnecessary stress on the haul trucks.

Tight Tolerances

Trans Ash made use of our experienced in-house surveyors and extensive GPS controlled equipment fleet to achieve the design grades and thicknesses required in the specifications.

Contact the Team at Trans Ash for Your Next Project

Contact us today to see how our services can help you or your business. We’re able to answer any questions you have, provide a list of service offerings, and discuss future employment possibilities.

Want to learn more about Trans Ash? Visit our Markets & Solutions section, browse our Project Case Studies, or call us at 513-733-4770.