Project Overview

Due to new regulations, the sludge sediment basins at this coal-fired power plant required removal of the existing liner system and protective concrete cover. The basins were retrofitted with a new liner system meeting the requirements of Laws and Codes, including federal CCR rules and regulations.

"Trans Ash was able to work closely with the owner to reevaluate the schedule and modify the task priority list."

Project Challenges & Solutions

Several items were encountered throughout the life cycle of this project and created the following challenges:

  • Due to permitting delays, the majority of the project was executed during the fall and winter months. The weather encountered during this time of year caused setbacks in the schedule. Trans Ash was able to work closely with the owner to re-evaluate the schedule and modify the task priority list.
  • During demolition, CCR’s were found outside the limits of the existing liner system. This impacted the quantity of existing onsite clay that was planned to be re-used. Fortunately, the borrow source for the new clay liner was adequate enough to provide material to account for the negative balance in subgrade fill.
  • Several large rain events caused project delays. The low permeability borrow source was located on a piece of property on the opposite side of the river from the project site. During a flood event, the bridge used for crossing the river was closed and haul trucks had to be re-routed. This caused a significant impact to the haul distance so additional trucks were mobilized to ensure production rates were maintained.
  • During the electrical system replacement, an existing duct bank was found to be located in an unexpected location. This required the duct bank to be relocated earlier in the project than originally anticipated, which impacted the liner system installation phasing. Trans Ash worked jointly with the design engineer and owner to implement the best solution to this problem.
Download Case Study (PDF)
Concrete Liner Install

Project Scope Highlights

  • Dewatered and removed CCRs from two concrete-lined basins.
  • Demolished, removed, and disposed of rip rap and concrete to offsite landfill.
  • Installed a new 2-foot geologic buffer layer of low permeability clay from an offsite source.
  • Installed a new geosynthetic liner system consisting of a 60 mil HDPE geo-membrane and 12 oz non-woven textile.
  • Installed 5,500 CY of 4,000 PSI concrete over entire foot print of the liner system.
  • Constructed a new concrete pump station.
  • Installed 2,500’ HDPE piping used for effluent and return water.
  • Replaced all existing electrical components for the new pump system.
  • Utilized a temporary by-pass pump to and Port-A-Dam system to maintain plant operations.
Electrical Duct Bank Install
Subgrade preparation
Complete Pump Station
Completed Sludge Sediment Basin

Discover how Trans Ash can Help your Business Thrive

We provide labor, material, equipment, and decades of expertise. With all of these assets, we go the extra mile for our clients, designing creative solutions, adapting to your project needs, and getting the job done.

Call us today at 513.733.4770 or fill out send us a message to discover how we can help meet your next challenge.

Contact Trans Ash