Project Overview

Due to the new state CCR regulations, the CCR basin at this retired, coal-fired facility required clean closure. This clean closure necessitated the construction of an on-site CCR landfill. This high visibility project had a state-mandated completion date and almost constant scrutiny by the media and both government and non-government environmental groups.

"Trans Ash’s construction plan ensured environmental and engineering compliance. Extensive erosion control safeguards and containment systems were used throughout the project."

Project Challenges & Solutions

The timing of the construction and the state-mandated schedule created the following challenges:

  • Trans Ash worked concurrently with an existing contractor who was removing CCRs for a beneficial use project. Consequently, the landfill construction space was restricted and required an updated construction sequence. Trans Ash worked cooperatively with the client to re-evaluate the schedule and devise an appropriate phasing plan.
  • An on-site wetland created some traffic flow and accessibility issues. Trans Ash followed a strict ES&C plan to address this issue and protect the wetland.
  • Due to previous environmental issues and proximity to the river, this was a heavily scrutinized project with much local interest. Trans Ash’s construction plan ensured environmental and engineering compliance. Extensive erosion control safeguards and containment systems were used throughout the project.
  • The clay available at the on-site borrow area did not meet specifications in its original state. Trans Ash utilized a screening system to ensure all the non-spec material was removed.
  • The landfill leachate collection system required a tie-in with the local municipality’s water treatment system. Trans Ash coordinated a strict tie-in schedule with the client, the certified sub-contractor, and the city to ensure there was no interruption of service to the surrounding community.
  • During construction, a previously unidentified, asbestos disposal site was discovered. Trans Ash immediately ceased activity, isolated the area, and contacted the
    client. A remediation sub-contractor was utilized to remove the material.
  • Midway through the project, the on-site CCR removal contractor was replaced. This change limited the available CCRs required for the liner system protective cover. Trans Ash modified the construction schedule and created a communication plan to coordinate activities with the new contractor.
Download Case Study (PDF)
Leachate Collection Pipe Cover

Project Scope Highlights

  • Construct leachate tank and force main
  • Installed 2,500 ft. dual contained HDPR force main pipe
  • Compacted fill placement
  • Clear and grub
  • Liner placement
  • Install leachate collection system
  • Place a protective cover over liner
  • Construct hydro turf perimeter ditch
Sub Surface Grading
Liner Installation
Concrete Demo
Demo Concrete Removal

Discover how Trans Ash can Help your Business Thrive

We provide labor, material, equipment, and decades of expertise. With all of these assets, we go the extra mile for our clients, designing creative solutions, adapting to your project needs and getting the job done.

Call us today at 513.733.4770 or fill out send us a message to discover how we can help meet your next challenge.

Contact Trans Ash